700 MW NUCLEAR POWER PLANT KAPS-4

TAG: GS 3: SCIENCE AND TECHNOLOGY

THE CONTEXT: On August 21, 2024, India’s second home-built 700 MW nuclear power reactor at Kakrapar Atomic Power Station (KAPS) in Gujarat, known as KAPS-4, began operating at its full capacity.

EXPLANATION:

  • This milestone represents a significant achievement for India’s nuclear power sector, underscoring the capabilities of indigenous nuclear technology.

KAPS-4

  • The KAPS-4 unit first achieved criticality on December 17, 2023, marking the beginning of its operational phase.
  • Following this, the reactor commenced commercial operations on March 31, 2024.
  • Since then, it had been gradually increasing its power output, operating at 90% capacity before reaching its full power of 700 MWe.
  • The Nuclear Power Corporation of India Limited (NPCIL), which operates the plant, confirmed this development, highlighting the success of KAPS-4’s performance.
  • The full-power operation of KAPS-4, along with its twin unit KAPS-3, which is already operating at full capacity, showcases the robustness of India’s indigenous 700 MW Pressurised Heavy Water Reactor (PHWR) design.
  • The NPCIL emphasized that this achievement reflects the strength and reliability of India’s first-of-a-kind nuclear reactor design.
  • The successful deployment and operation of these reactors are crucial milestones in India’s quest for energy self-sufficiency and sustainable development.

Regulatory Approvals and Safety Compliance

  • The progression of KAPS-4 to full power was carried out in compliance with the guidelines and permissions granted by the Atomic Energy Regulatory Board (AERB).
  • The AERB plays a critical role in ensuring the safety and regulatory compliance of nuclear power operations in India.
  • The controlled and systematic increase in the reactor’s power level indicates stringent adherence to safety protocols, which is essential for maintaining public and environmental safety.

Future Expansion Plans

  • India is not stopping with KAPS-3 and KAPS-4.
  • The country has ambitious plans to expand its nuclear power capabilities.
  • There are 14 more reactors of the same 700 MW design currently under construction, scheduled to commence operations progressively by 2031-32.
  • This expansion plan is part of India’s strategy to meet its growing energy demands and reduce its dependence on fossil fuels.

Nuclear Capacity

  • At present, NPCIL operates a fleet of 24 nuclear reactors with a total installed capacity of 8,180 MW.
  • Additionally, there are eight units under construction with a combined capacity of 6,800 MW.
  • In pre-project stages, there are 10 more reactors, expected to add 7,000 MW to the country’s nuclear power capacity.
  • Once these projects are completed, India’s installed nuclear power capacity is projected to reach 22,480 MW by 2031-32.

Strategic Importance of Nuclear Energy in India

  • The development and expansion of nuclear power in India hold significant strategic importance.
  • As the country’s energy needs continue to grow, nuclear energy provides a reliable, low-carbon source of power.
  • It plays a crucial role in India’s energy mix, helping to reduce greenhouse gas emissions and meet climate change commitments.
  • The successful operation of KAPS-4 at full capacity demonstrates India’s commitment to leveraging advanced nuclear technology for sustainable development.

SOURCE: https://www.thehindu.com/news/national/indias-second-700-mw-nuclear-power-kaps-4-plant-starts-operations-at-full-capacity/article68549652.ece#:~:text=The%20KAPS%2D4%20unit%20achieved,commercial%20operations%20on%20March%2031&text=India%27s%20second%20home%2Dbuilt%20700,capacity%2C%20the%20plant%20operator%20said

Spread the Word